Comment: updated timelines

...

In June 2017 phase 1 of the project was completed, and phase 2 started. In phase 1, use cases were drawn up and coordinated with a number of cooperative organisations, an architecture was drawn up and needs were assessed. Phase 2, which runs from now until the third 2nd quarter of 20182010, is dedicated to realising the various components and gaining experience through pilots.

...

  • Aug / Sep 2017 - Establish pilot environment
  • Oct / Nov 2017 - Connecting backend systems
  • Oct / Nov 2017 - Set up and test deployment flows
  • Oct-Dec 2017 - Set up and fine-tune access for external people / guests / etc
  • Dec 2017 - Dec 2018 Jun 2019 - Pilot with the pilot environment:
    • Access for "ordinary" (pilot) users
    • Finetuning flows
    • Connect more services
    • Develop the platform
  • Q4 2018 Jun 2019 - go / no go SCZ phase 3 (service development or realised controlled phasing out)
  • Until the end of 2018 2019 - Regardless of the decision (go or no go) pilot partners will be supported until the end of 20182019.